List of Marine Works in Progress in Hong Kong

Please download and install the Adobe Acrobat Reader to view and print documents in PDF.


Date : till 14 Apr 2010
Type :Dredging, Piling, Site Investigation and Reclamation Works
Location : Central Harbour
MDN ref. MDN No. 51 of 2009 (PDF)


Date : till 10 Oct 2010
Type :Seawall Construction Works
Location : at Middle Island
MDN ref. MDN No. 59 of 2009 (PDF)


ate : till 10 May 2010
Type :Temporary Establishment of a Current Meter
Location : off Yau Kom Tau and at Western Dangerous Goods Anchorage
MDN ref. MDN No. 62 of 2009 (PDF)


Date : till 2 Aug 2011
Type :Widening Works
Location : Tai Lam Bridge, Tuen Mun Road
MDN ref. MDN No. 102 of 2009 (PDF)


Date : till 23 Aug 2013
Type : Dredging Operations
Location : North of the Hong Kong International Airport
MDN ref. MDN No. 110 of 2009 (PDF)


Date : till 15 Apr 2010
Type : Extension Works to a Pier and Dredging Operations
Location : off Tap Shek Kok, Urmston Road
MDN ref. MDN No. 120 of 2009 (PDF)


Date : till 26 Mar 2010
Type : Re-construction Works to a Public Pier
Location : Leung Shuen Wan, Sai Kung
MDN ref. MDN No. 144 of 2009 (PDF)


Date : till 31 Jul 2011
Type : Silt Curtain
Location : Tai Shue Wan, South of Hong Kong Island
MDN ref. MDN No. 149 of 2009 (PDF)


Date : till 20 Mar 2010
Type : Rubble Removal and Sand Replenishment Works
Location : Lo So Shing Beach, Lamma Island
MDN ref. MDN No. 174 of 2009 (PDF)


Date : till 1 Jul 2013
Type : Construction of Drainage Outfall
Location : Yau Kom Tau
MDN ref. MDN No. 179 of 2009 (PDF)


Date : till 3 Jul 2010
Type : Marine Site Investigation
Location : off Hong Kong International Airport
MDN ref. MDN No. 2 of 2010 (PDF)


Date : till 5 Apr 2010
Type : Demolition of Temporary Piers
Location : the East of Hong Kong Disneyland
MDN ref. MDN No. 5 of 2010 (PDF)


Date : till 14 May 2011
Type : Seawall Reinstatement, Landing Steps Construction and Drainage Outfall Reconstruction Works
Location : Tseung Kwan O
MDN ref. MDN No. 6 of 2010 (PDF)


Date : till 28 Mar 2010
Type : Sand Replenishment Works
Location : Stanley Main Beach
MDN ref. MDN No. 9 of 2010 (PDF)


Date : till 2 Nov 2010
Type : Maintenance Dredging
Location : Kau Yi Chau Dangerous Goods Anchorage
MDN ref. MDN No. 13 of 2010 (PDF)


Date : till 27 Apr 2010
Type : Marine Site Investigation
Location : Kwun Tong Typhoon Shelter and Kai Tak Nullah
MDN ref. MDN No. 15 of 2010 (PDF)


Date : till 4 Aug 2010
Type : Seawall Construction Works
Location : Kwun Tong Typhoon Shelter and Kai Tak Nullah
MDN ref. MDN No. 19 of 2010 (PDF)


Date : till 3 Jun 2010
Type : Removal and Laying of Private Moorings
Location : Aberdeen South Typhoon Shelter
MDN ref. MDN No. 20 of 2010 (PDF)


Date : till 3 Apr 2010
Type : Submarine Pipeline Repair Works
Location : Urmston Road
MDN ref. MDN No. 21 of 2010 (PDF)


Date : till 4 Apr 2010
Type : Marine Site Investigation
Location : Junk Bay
MDN ref. MDN No. 22 of 2010 (PDF)


Date : till 4 Apr 2010
Type : Dredging Operations
Location : off West Coast of Lamma Island
MDN ref. MDN No. 23 of 2010 (PDF)


Date : till 9 Oct 2011
Type : Site Investigation, Dredging and Reclamation Works
Location : off North Point
MDN ref. MDN No. 24 of 2010 (PDF)


Date : till 12 Apr 2010
Type : Marine Site Investigation
Location : Causeway Bay Typhoon Shelter
MDN ref. MDN No. 27 of 2010 (PDF)


Date : till 3 Apr 2010
Type : Dredging Operations
Location : off Kwai Chung Container Terminal 9
MDN ref. MDN No. 28 of 2010 (PDF)


Date : till 25 Apr 2010
Type : Dredging Operations
Location : Marina Cove, Sai Kung
MDN ref. MDN No. 29 of 2010 (PDF)


Last revision date : 15 March 2010

Close